Dinish Wharf Completion Works Project Update
We have successfully completed the installation of the new sheet piled western cell as part of the western breakwater. In early 2022, we will extend the land to the cell to form the completed western breakwater. Operations on the quay extension are also ongoing with the placement of precast beams. Dredging of the soft material in the berth pocket and navigation channel continues to progress and in January we will transfer the 170T excavator onto the barge to commence rock breaking in the berth pocket. Well done to all involved to date.