Dinish Wharf Project Update

Fantastic progress has been made by our site team in Dinish Island in recent weeks. The piling works on cell 3, which forms part of the eastern breakwater, is nearing completion. The cell is 17.3m in diameter and requires 108 flat piles to be installed to form its circumference. The RC bank seat of the extension for the quay deck has also been completed with works on the steel piles ready to commence in preparation for the delivery of precast units. Foyle and Marine Dredging continue to carry out dredging works in the basin and will move into the navigation channel and berth pocket in the coming weeks.

 