General Description

This project involved the construction of 12Km of sewer gravity & rising mains and a 200m long crossing of the river Shannon.

Features
  • 12Km of gravity and pressure sewer pipe lines
  • 200m long crossing of the Shannon river
  • Trench excavation by long-reach excavators mounted on a floating pontoon
  • 6 no. High density polyethylene (HDPE) pipelines (2 rising mains, 2 water mains & 2 service pipes) were welded on shore, inserted into specially constructed steel frames, floated into position and sunk using the steel frames as ballast
  • 2 new RC Reservoirs & refurbishment of 3 existing reservoirs
  • Pumping station
  • Control building
  • Site works